Budapest Central Wastewater Treatment Plant

From 2011 NovoProject acted as FIDIC engineer and technical supervisor in the construction of the Budapest Central Wastewater Treatment Plant project and related facilities as a subcontractor. Due to the increased volume of tasks a public procurement tender was launced for the FIDIC engineering and technical supervision tasks which was also won by NovoProject.

NovoProject also acted as FIDIC engineer and technical supervisor during the construction of nearly 10 kilometres of new sewage system built with the support of the Cohesion Fund of the European Union. The overall value of the constructoion reached nearly EUR 20 million.